Crew A can finish a renovation in 10 days working alone. Crew B can finish it in 15 days working alone. Crew A works alone for 4 days, and then both crews work together until the job is done.
How many days do the two crews work together?
- 2.4
- 3
- 3.6
- 4
- 6