hard · GMAT Quant
Worker A is twice as efficient as worker B. A works alone on a project for 4 days, after which B joins and the two of them work together for 4 more days, completing the entire project.
How many days would worker B alone have needed to complete the entire project?
- 8 days
- 10 days
- 16 days
- 20 days
- 24 days
Sign up free to see the explanation and track your rank →
More GMAT Quant practice
- Including both endpoints, how many distinct integer price points are in this range?
- Which of the following expressions must result in a positive value?
- Which property of arithmetic justifies that first step?
- Which of the following must also be an even integer?
- Which of the following inequalities correctly represents this range?
- Which of the following includes the number 0?
- How many unique meal combinations can a customer create?
- What is the probability that the lightbulb is functional?