During the construction of the Ironvale Grid transmission line, the project manager identifies a significant point in time with no duration that marks the completion of the environmental impact study.

How should this be represented in the schedule?

  1. As a Summary Activity
  2. As a Milestone
  3. As a Work Package
  4. As a Control Account