A project manager at Quill Digital is finishing a predictive marketing automation project. The client is happy with the results, but the project manager's supervisor wants the project closed immediately to start a new high-priority initiative. The lessons learned meeting is scheduled for next week.

What is the best action?

  1. Start the new project and run the lessons learned meeting for the old project in the evenings.
  2. Close the project now and ask the team to submit their lessons via email later.
  3. Cancel the meeting and archive the current documents to meet the supervisor's request.
  4. Conduct the lessons learned meeting as planned before completing closure.