easy · Project Management Professional Predictive (Plan-Driven)
The city council at Kestrel Civic is reviewing a final project report. They notice that the project finished on time and on budget, but the intended benefits (reduced traffic congestion) are not yet visible.
What should the project manager have included in the closure documents to address this?
- A request for a six-month extension to monitor the traffic personally.
- A benefits realization plan with a named owner and a measurement schedule.
- A guarantee that the congestion will decrease within one year.
- A statement that the project manager is no longer responsible for benefits after the bridge is open.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
- An activity on the Valeport Energy project has an Early… What can be concluded about this…
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards