medium · Project Management Professional predictive
Hearthline Energy has calculated a net EMV of -$10,000 for its predictive project.
If the organization has a very low risk appetite and a strict risk threshold of $5,000 for any project variation, what is the project manager's best action?
- Report the $10,000 EMV and ask the sponsor to increase the risk threshold.
- Develop additional risk response strategies to mitigate or transfer the threats until the EMV is within the $5,000 threshold.
- Ignore the threshold and use the $10,000 reserve, as it is based on sound math, after reviewing the current risk register entries.
- Switch to an adaptive delivery model where risk thresholds are not measured.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?