medium · Project Management Professional predictive
A Coveport project manager is calculating the PTA for a vendor contract. The values are: Ceiling Price = 1,250,000, Target Cost = 1,000,000, Target Fee = 100,000, and Buyer Share Ratio = 0.8. The PM's calculation results in 1,187,500.
What does this PTA value represent in terms of seller risk?
- The cost level where the seller's fee is exactly zero.
- The point where the project manager must escalate to the Change Control Board for more funding.
- The maximum amount the buyer will ever have to pay for the contracted work.
- The point beyond which the seller bears 100% of every additional dollar of cost.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?