medium · Project Management Professional predictive
Coveport Logistics is updating its predictive tracking software. The team identifies a server failure risk (EMV: -$6,000) and a data breach threat (EMV: -$12,000), alongside a cloud credits opportunity (EMV: +$8,000). After setting the contingency reserve to $10,000, the project manager notices the server failure probability has increased.
What should the project manager do next?
- Inform the sponsor that a budget overrun is now inevitable.
- Immediately move $10,000 from management reserve into the cost baseline, while documenting the decision in the issue log.
- Direct the developers to work overtime to avoid the server failure.
- Update the risk register and re-perform the EMV calculation to assess reserve adequacy.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?