hard · Project Management Professional predictive
A Harborline Transit FPIF contract is at the settlement stage after several changes. The final Actual Cost is 2,100,000, which is above the PTA of 1,950,000 and the Ceiling Price of 2,050,000.
What should the project manager do regarding the final payment?
- Pay the actual cost of 2,100,000 to maintain a good relationship with the vendor.
- Negotiate a 50/50 split of the 50,000 difference between the ceiling and actual cost.
- Submit a change request to increase the budget to cover the seller's total costs.
- Pay the ceiling price of 2,050,000 as the final settlement.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?