A project at Hearthline Energy is in the planning phase. The project manager is identifying risks. One risk is that a new environmental law might pass. The project manager decides to design the plant to meet the potential new standard now to avoid a costly retrofit later. This strategy is:

  1. Acceptance
  2. Transference
  3. Mitigation
  4. Avoidance