medium · Project Management Professional predictive
A Quayport Logistics project involves the following data points: | Data | Value | |:--- |:--- | | BAC | 1,000,000 | | EV | 250,000 | | AC | 200,000 | If the project manager believes the current favorable cost performance is systemic, what VAC should be reported?
- 50,000
- -200,000
- 200,000
- 0