easy · Project Management Professional predictive
A road paving initiative at Westfork Municipal reports an AC of $60,000, a PV of $45,000, and an EV of $50,000. Calculate the CPI and SPI.
- CPI = 0.75; SPI = 1.33
- CPI = 0.83; SPI = 1.11
- CPI = 1.11; SPI = 0.83
- CPI = 1.20; SPI = 0.90