medium · Project Management Professional predictive

A project manager at Hearthline Energy is overseeing a predictive substation build. A primary vendor announces a late delivery for specialized transformers.

Before informing the sponsor of a potential delay, which action should the project manager take first?

  1. Inform the sponsor that the project completion date will slip by two weeks, before confirming the relevant stakeholders agree.
  2. Analyze the project schedule to determine if the delivery is on the critical path.
  3. Escalate the vendor's performance issue to the procurement director.
  4. Submit a change request to the CCB to extend the schedule baseline.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials