A project manager at Hearthline Energy is overseeing a predictive substation build. A primary vendor announces a late delivery for specialized transformers.

Before informing the sponsor of a potential delay, which action should the project manager take first?

  1. Inform the sponsor that the project completion date will slip by two weeks, before confirming the relevant stakeholders agree.
  2. Analyze the project schedule to determine if the delivery is on the critical path.
  3. Escalate the vendor's performance issue to the procurement director.
  4. Submit a change request to the CCB to extend the schedule baseline.