medium · Project Management Professional predictive
A project manager at Hearthline Energy is overseeing a predictive substation build. A primary vendor announces a late delivery for specialized transformers.
Before informing the sponsor of a potential delay, which action should the project manager take first?
- Inform the sponsor that the project completion date will slip by two weeks, before confirming the relevant stakeholders agree.
- Analyze the project schedule to determine if the delivery is on the critical path.
- Escalate the vendor's performance issue to the procurement director.
- Submit a change request to the CCB to extend the schedule baseline.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?