KomFi. Academy

medium · Project Management Professional Predictive (Plan-Driven)

The project manager at Trestle Ports has calculated a critical path expected duration of 100 days with a path standard deviation of 4 days.

Between which range of days can the project manager be approximately 95% confident the project will finish?

  1. 98 to 102 days
  2. 92 to 108 days
  3. 88 to 112 days
  4. 96 to 104 days

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards