medium · Project Management Professional Predictive (Plan-Driven)
The project manager at Trestle Ports has calculated a critical path expected duration of 100 days with a path standard deviation of 4 days.
Between which range of days can the project manager be approximately 95% confident the project will finish?
- 98 to 102 days
- 92 to 108 days
- 88 to 112 days
- 96 to 104 days
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards