Bramble Civic is constructing a new library. A stakeholder group demands a change to the floor plan during execution.

Following the predictive mindset, how should the project manager respond?

  1. Reject the change as the scope baseline has already been approved.
  2. Implement the change immediately to ensure stakeholder satisfaction.
  3. Document the request and perform an impact analysis across all project constraints.
  4. Escalate the request to the Change Control Board (CCB) for an immediate decision.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials