Bramble Civic is constructing a new library. A stakeholder group demands a change to the floor plan during execution.
Following the predictive mindset, how should the project manager respond?
- Reject the change as the scope baseline has already been approved.
- Implement the change immediately to ensure stakeholder satisfaction.
- Document the request and perform an impact analysis across all project constraints.
- Escalate the request to the Change Control Board (CCB) for an immediate decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards