The Hearthline Energy project manager is holding a status meeting on Tuesday and a stage gate on Thursday.

How do the objectives of these two meetings differ?

  1. Status is for the sponsor; the gate is only for the project team members, before confirming the relevant stakeholders agree.
  2. Status is used to approve changes; the gate is used to identify risks.
  3. Status focuses on progress and variances; the gate focuses on investment viability and phase transition.
  4. Status is a predictive ceremony; the gate is an adaptive ceremony.