easy · Project Management Professional predictive
A PM at Hearthline Energy is decomposing the 'Grid Interconnect' work package into activities. A team member asks if the 'Final Inspection' activity should be added as a child in the WBS.
How should the PM proceed?
- Direct the team member to perform the inspection immediately without documentation.
- Include the inspection in the WBS as a Level 4 child to satisfy the 100% rule.
- Add the inspection to the activity list while keeping the WBS focused on the deliverable.
- Update the project scope statement to include the inspection as a project exclusion, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?