Harborline Transit is using a predictive approach for a new depot. The PM is asked to 'rebaseline' the project because of a 2-day delay in painting.

How should the PM respond?

  1. Submit a change request to the CCB to rebaseline immediately.
  2. Update the schedule baseline manually without a change request.
  3. Ask the team to work overtime to ensure the baseline never has to be looked at, after reviewing the current risk register entries, without revisiting the agreed prioritization criteria.
  4. Inform the stakeholder that rebaselining is for significant changes, not minor variances that don't affect the project's overall viability.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials