A Harborline Transit stakeholder is upset that the 'Physical Resource Assignments' are not in the PM plan.

How should the PM respond?

  1. Escalate to the Resource Manager to find out why they didn't put the assignments in the plan, before confirming the relevant stakeholders agree.
  2. Submit a change request to add the bus assignments to the PM plan.
  3. Explain that physical resource assignments are project documents, not part of the baselined PM plan.
  4. Tell the stakeholder they are looking at the wrong version of the PM plan.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials