easy · Project Management Professional predictive
A Harborline Transit stakeholder is upset that the 'Physical Resource Assignments' are not in the PM plan.
How should the PM respond?
- Escalate to the Resource Manager to find out why they didn't put the assignments in the plan, before confirming the relevant stakeholders agree.
- Submit a change request to add the bus assignments to the PM plan.
- Explain that physical resource assignments are project documents, not part of the baselined PM plan.
- Tell the stakeholder they are looking at the wrong version of the PM plan.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?