At Valeport Energy, a predictive project to upgrade power grid sensors relies on a single vendor for encryption chips. The vendor has just filed for bankruptcy.

How should the project manager categorize this situation?

  1. As a high-impact risk that requires an immediate update to the risk register.
  2. As a change request to the cost baseline to account for higher prices from a new vendor.
  3. As a secondary risk arising from the original procurement management plan.
  4. As an issue that requires the implementation of the planned contingency response.