Willowbrook Schools is renovating three computer labs. The project has a cost baseline of $150,000 and a contingency reserve of $15,000. A identified risk regarding a hardware shortage occurs, and the response will cost $5,000.

How should the project manager handle the funding?

  1. Use $5,000 from the contingency reserve as planned and update the risk register.
  2. Submit a change request to increase the cost baseline by $5,000. given the information provided
  3. Absorb the cost by reducing the scope of the software installation.
  4. Request $5,000 from the management reserve from the school district.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials