hard · Project Management Professional predictive
In a predictive project at Nimbus Clinics, the funding limit reconciliation for Q4 requires deferring work that will consume 5 days of total float. The project has 10 days of total float.
How should the project manager handle this?
- Inform the team that the project is now 5 days behind schedule.
- Request more funding for Q4 to avoid losing the 5 days of float.
- Update the schedule model to show the new dates and document the reduction in float.
- Submit a change request to the CCB because float is a baselined component, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?