hard · Project Management Professional predictive

In a predictive project at Nimbus Clinics, the funding limit reconciliation for Q4 requires deferring work that will consume 5 days of total float. The project has 10 days of total float.

How should the project manager handle this?

  1. Inform the team that the project is now 5 days behind schedule.
  2. Request more funding for Q4 to avoid losing the 5 days of float.
  3. Update the schedule model to show the new dates and document the reduction in float.
  4. Submit a change request to the CCB because float is a baselined component, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials