In a predictive project at Nimbus Clinics, the funding limit reconciliation for Q4 requires deferring work that will consume 5 days of total float. The project has 10 days of total float.

How should the project manager handle this?

  1. Inform the team that the project is now 5 days behind schedule.
  2. Request more funding for Q4 to avoid losing the 5 days of float.
  3. Update the schedule model to show the new dates and document the reduction in float.
  4. Submit a change request to the CCB because float is a baselined component, without revisiting the agreed prioritization criteria.