A hybrid project at Whitlock Software has an infrastructure team using predictive methods and a development team using Scrum. The infrastructure team finishes its work two weeks early.

How should the project manager handle this variance?

  1. Analyze the impact on the development team's sprint dependencies and update the integrated project schedule.
  2. Direct the development team to start their next sprint early to take advantage of the gain.
  3. Rebaseline the project schedule immediately to reflect the early completion.
  4. Submit a change request to the CCB to reduce the project's total budget by the saved amount, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards