medium · Project Management Professional predictive

A hybrid project at Whitlock Software has an infrastructure team using predictive methods and a development team using Scrum. The infrastructure team finishes its work two weeks early.

How should the project manager handle this variance?

  1. Analyze the impact on the development team's sprint dependencies and update the integrated project schedule.
  2. Direct the development team to start their next sprint early to take advantage of the gain.
  3. Rebaseline the project schedule immediately to reflect the early completion.
  4. Submit a change request to the CCB to reduce the project's total budget by the saved amount, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials