A safety inspector at Bramble Civic identifies a structural weakness in a public walkway that must be shored up within 2 hours. The construction lead disagrees with the inspector's assessment.

How should the project manager proceed?

  1. Direct the lead to clear the walkway and begin the shoring work as specified by the inspector.
  2. Facilitate a problem-solving session to find a middle ground between the inspector and the lead.
  3. Request the team lead to document the disagreement in the issue log for a meeting tomorrow.
  4. Ask the sponsor to mediate the technical dispute between the lead and the inspector.