medium · Project Management Professional predictive

A safety inspector at Bramble Civic identifies a structural weakness in a public walkway that must be shored up within 2 hours. The construction lead disagrees with the inspector's assessment.

How should the project manager proceed?

  1. Direct the lead to clear the walkway and begin the shoring work as specified by the inspector.
  2. Facilitate a problem-solving session to find a middle ground between the inspector and the lead.
  3. Request the team lead to document the disagreement in the issue log for a meeting tomorrow.
  4. Ask the sponsor to mediate the technical dispute between the lead and the inspector.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials