medium · Project Management Professional predictive

At Solstice Labs, the project manager finds that the current Schedule Performance Index (SPI) is 1.15 and the Cost Performance Index (CPI) is 0.78.

How should the project's status be reported to the sponsor?

  1. The project is performing exactly as planned because the indices average out to nearly 1.0.
  2. The project is behind schedule and under budget.
  3. The project is ahead of schedule and under budget.
  4. The project is ahead of schedule but over budget.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials