At Solstice Labs, the project manager finds that the current Schedule Performance Index (SPI) is 1.15 and the Cost Performance Index (CPI) is 0.78.

How should the project's status be reported to the sponsor?

  1. The project is performing exactly as planned because the indices average out to nearly 1.0.
  2. The project is behind schedule and under budget.
  3. The project is ahead of schedule and under budget.
  4. The project is ahead of schedule but over budget.

Sign up free to see the explanation and track your rank →