medium · Project Management Professional predictive

A software team at Plover Software has a historical velocity of 30 story points per sprint. For the upcoming sprint, two senior developers will be on leave for the entire two weeks.

How should the team determine their commitment for the next sprint?

  1. Maintain the 30-point commitment to encourage the remaining team members to work faster.
  2. Record a velocity of zero for those developers and keep the rest of the plan the same.
  3. Calculate the team's capacity for the sprint and adjust the commitment down.
  4. Ask the Product Owner to select fewer items based on the developers' absence.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials