medium · Project Management Professional predictive
A software team at Plover Software has a historical velocity of 30 story points per sprint. For the upcoming sprint, two senior developers will be on leave for the entire two weeks.
How should the team determine their commitment for the next sprint?
- Maintain the 30-point commitment to encourage the remaining team members to work faster.
- Record a velocity of zero for those developers and keep the rest of the plan the same.
- Calculate the team's capacity for the sprint and adjust the commitment down.
- Ask the Product Owner to select fewer items based on the developers' absence.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?