medium · Project Management Professional Predictive (Plan-Driven)

Fenwick Grid is implementing a new 'Sustainable Supply Chain' policy. The project manager has data from three recent vendors who failed to meet environmental standards.

How should this data be 'Combined' into the OPAs?

  1. Escalate the vendor failures to the Environmental Protection Agency (EPA) for investigation, before confirming the relevant stakeholders agree.
  2. Incorporate the 'Failure Patterns' into the vendor pre-qualification checklist for future procurements.
  3. Blacklist the three vendors and notify the legal department immediately.
  4. Ask the procurement team to 'be more careful' when selecting vendors in the future.