Fenwick Grid projects must follow the 'Rule of Seven' on their control charts.
If a project manager brings a control chart to a gate showing eight consecutive points above the mean, what should the committee conclude?
- The team should immediately switch to a 'Retrospective' to fix it, before confirming the relevant stakeholders agree.
- A non-random 'assignable cause' exists and must be investigated before the phase is closed.
- The project is performing 14.3% better than average.
- The chart should be deleted before the sponsor sees it.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?