Fenwick Grid projects must follow the 'Rule of Seven' on their control charts.

If a project manager brings a control chart to a gate showing eight consecutive points above the mean, what should the committee conclude?

  1. The team should immediately switch to a 'Retrospective' to fix it, before confirming the relevant stakeholders agree.
  2. A non-random 'assignable cause' exists and must be investigated before the phase is closed.
  3. The project is performing 14.3% better than average.
  4. The chart should be deleted before the sponsor sees it.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials