medium · Project Management Professional predictive

A project manager at Coveport Logistics is tracking the schedule. Activity G has a total float of 5 days and a free float of 0 days.

If Activity G is delayed by 3 days, what is the effect on the project?

  1. Neither the successor nor the project finish date will be affected, before confirming the relevant stakeholders agree.
  2. The project finish date will be delayed by 3 days.
  3. The project finish date remains unchanged, but the early start of the successor is delayed.
  4. The activity must be crashed to avoid a critical path shift.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials