medium · Project Management Professional predictive
A project manager at Coveport Logistics is tracking the schedule. Activity G has a total float of 5 days and a free float of 0 days.
If Activity G is delayed by 3 days, what is the effect on the project?
- Neither the successor nor the project finish date will be affected, before confirming the relevant stakeholders agree.
- The project finish date will be delayed by 3 days.
- The project finish date remains unchanged, but the early start of the successor is delayed.
- The activity must be crashed to avoid a critical path shift.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?