A project manager at Coveport Logistics is tracking the schedule. Activity G has a total float of 5 days and a free float of 0 days.

If Activity G is delayed by 3 days, what is the effect on the project?

  1. Neither the successor nor the project finish date will be affected, before confirming the relevant stakeholders agree.
  2. The project finish date will be delayed by 3 days.
  3. The project finish date remains unchanged, but the early start of the successor is delayed.
  4. The activity must be crashed to avoid a critical path shift.