KomFi. Academy

medium · Project Management Professional Predictive (Plan-Driven)

Coveport Logistics is using an FPIF contract for a conveyor system. Target Price = 1,100,000, Ceiling Price = 1,250,000, Target Cost = 1,000,000, and Buyer Share = 80%.

If the actual cost is 1,200,000, which is above the calculated PTA of 1,187,500, what is the final fee for the seller?

  1. 60,000
  2. 100,000
  3. 0
  4. 50,000

Sign up free to see the explanation and track your rank →