Coveport Logistics is using an FPIF contract for a conveyor system. Target Price = 1,100,000, Ceiling Price = 1,250,000, Target Cost = 1,000,000, and Buyer Share = 80%.
If the actual cost is 1,200,000, which is above the calculated PTA of 1,187,500, what is the final fee for the seller?
- 60,000
- 100,000
- 0
- 50,000