Coveport Logistics is using an FPIF contract for a conveyor system. Target Price = 1,100,000, Ceiling Price = 1,250,000, Target Cost = 1,000,000, and Buyer Share = 80%.

If the actual cost is 1,200,000, which is above the calculated PTA of 1,187,500, what is the final fee for the seller?

  1. 60,000
  2. 100,000
  3. 0
  4. 50,000

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials