medium · Project Management Professional predictive
Quayport Logistics is overseeing a harbor crane installation with a BAC of 2,000,000. At the mid-project review, the project manager identifies an EV of 800,000 and an AC of 1,000,000.
If the current cost variance is systemic, what is the EAC?
- 2,200,000
- 2,000,000
- 1,200,000
- 2,500,000