medium · Project Management Professional Predictive (Plan-Driven)

Valeport Energy is building a battery storage facility. 600 errors are noted: Cell Overheating (320), Cooling Pump Failure (160), Casing Dent (80), and Paint Scratch (40).

If the PM is performing Manage Quality, what is the correct action?

  1. Fix the casing dents and re-paint the scratched areas.
  2. Review the cell assembly quality standards and the pump testing protocols.
  3. Use a control chart to see if casing dents are occurring within the limits.
  4. Submit a change request to the CCB to replace all 600 batteries.