Larkspur Health's predictive project has two threats and one opportunity with EMV values.

If the probability of the opportunity increases from 0.4 to 0.8, while its impact remains +$80,000, what happens to the required contingency reserve?

  1. The project manager should immediately spend the difference on new hardware.
  2. The reserve stays the same, as opportunities don't affect contingency.
  3. The required reserve decreases because the positive EMV offset has doubled.
  4. The reserve increases because the project is now more uncertain.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials