medium · Project Management Professional predictive
Larkspur Health's predictive project has two threats and one opportunity with EMV values.
If the probability of the opportunity increases from 0.4 to 0.8, while its impact remains +$80,000, what happens to the required contingency reserve?
- The project manager should immediately spend the difference on new hardware.
- The reserve stays the same, as opportunities don't affect contingency.
- The required reserve decreases because the positive EMV offset has doubled.
- The reserve increases because the project is now more uncertain.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?