Bramble Civic is experiencing resource shortages. Two activities, Paving and Landscaping, share the same specialized crew. Paving is on the critical path.

If the project manager delays Landscaping to avoid extending the project finish date, which technique is being used?

  1. Fast Tracking
  2. Resource Leveling
  3. Crashing
  4. Resource Smoothing