Whitlock Software is executing a predictive system migration. A database corruption risk (probability 0.1, impact -$200,000) and a documentation error (probability 0.5, impact -$10,000) are identified. A legacy hardware sale opportunity exists (probability 0.2, impact +$50,000).

If the project manager establishes a contingency reserve of $15,000, which statement is true?

  1. The reserve is excessive because the project uses a predictive approach.
  2. The reserve is inadequate because the largest threat impact is $200,000.
  3. The reserve should be increased to $25,000 to exclude the uncertain opportunity.
  4. The reserve is adequate as it matches the absolute value of the net EMV.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards