Briarpoint Municipal is building a new park. A stage gate is held every three months.

If the project manager only reports that 'the swings are 50% installed,' what is missing for a proper Business Environment gate?

  1. The names of the vendors who supplied the swings.
  2. A re-assessment of risks and a confirmation of continued strategic alignment.
  3. An immediate escalation to the mayor for more park lighting, after reviewing the current risk register entries.
  4. The velocity of the landscaping team in 'Story Points'.