medium · Project Management Professional predictive
Stonehaven Transit is calculating EMV. Threat 1 (EMV: -$36,000), Threat 2 (EMV: -$20,000), and Opportunity 1 (EMV: +$32,000).
If the project manager reports a contingency reserve of $56,000, what is the fundamental error?
- The error is 'Wrong-Regime' because EMV is only for procurement.
- The error is 'Escalator' because the PM didn't ask for $100,000 to be safe.
- Failing to account for the opportunity offset, leading to an over-reserved budget.
- The error is 'Premature Actor' as the PM should have wait until closing to set the reserve.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?