Stonehaven Transit is calculating EMV. Threat 1 (EMV: -$36,000), Threat 2 (EMV: -$20,000), and Opportunity 1 (EMV: +$32,000).

If the project manager reports a contingency reserve of $56,000, what is the fundamental error?

  1. The error is 'Wrong-Regime' because EMV is only for procurement.
  2. The error is 'Escalator' because the PM didn't ask for $100,000 to be safe.
  3. Failing to account for the opportunity offset, leading to an over-reserved budget.
  4. The error is 'Premature Actor' as the PM should have wait until closing to set the reserve.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials