Stonehaven Transit is calculating EMV. Threat 1 (EMV: -$36,000), Threat 2 (EMV: -$20,000), and Opportunity 1 (EMV: +$32,000).

If the project manager reports a contingency reserve of $56,000, what is the fundamental error?

  1. The error is 'Wrong-Regime' because EMV is only for procurement.
  2. The error is 'Escalator' because the PM didn't ask for $100,000 to be safe.
  3. Failing to account for the opportunity offset, leading to an over-reserved budget.
  4. The error is 'Premature Actor' as the PM should have wait until closing to set the reserve.