At Hearthline Energy, a PM is using the 'Reporting Period' heuristic to size work packages.
If the status report is due every 14 days, what is the most defensible work package size for a grid update project?
- Work packages that can be completed within 14 to 28 days.
- All work packages must be exactly 80 hours according to the 8/80 rule.
- Work packages that always take exactly 14 days to ensure perfect reporting.
- The PM should assign all work packages as one-day tasks to maximize control.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards