easy · Project Management Professional predictive

At Hearthline Energy, a PM is using the 'Reporting Period' heuristic to size work packages.

If the status report is due every 14 days, what is the most defensible work package size for a grid update project?

  1. Work packages that can be completed within 14 to 28 days.
  2. All work packages must be exactly 80 hours according to the 8/80 rule.
  3. Work packages that always take exactly 14 days to ensure perfect reporting.
  4. The PM should assign all work packages as one-day tasks to maximize control.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials