At Hearthline Energy, a PM is using the 'Reporting Period' heuristic to size work packages.

If the status report is due every 14 days, what is the most defensible work package size for a grid update project?

  1. Work packages that can be completed within 14 to 28 days.
  2. All work packages must be exactly 80 hours according to the 8/80 rule.
  3. Work packages that always take exactly 14 days to ensure perfect reporting.
  4. The PM should assign all work packages as one-day tasks to maximize control.