hard · Project Management Professional Predictive (Plan-Driven)
Briarpoint Municipal is implementing a city-wide fiber network. At month 22 of 24, the SPI is 0.98 and the SV is -$40,000. The PM realizes that SPI is misleading.
If they decide to only report SV(t) and SPI(t) from now on, what must they do first?
- Consult the Communications Management Plan and the project's governance to ensure the change in reporting metrics is approved.
- Update the WBS to include 'Earned Schedule Analysis' as a new work package.
- Instruct the finance department to stop tracking AC since the focus is now on time.
- Stop all EVM data collection and focus only on the critical path in the schedule model, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards