hard · Project Management Professional predictive

Briarpoint Municipal is implementing a city-wide fiber network. At month 22 of 24, the SPI is 0.98 and the SV is -$40,000. The PM realizes that SPI is misleading.

If they decide to only report SV(t) and SPI(t) from now on, what must they do first?

  1. Consult the Communications Management Plan and the project's governance to ensure the change in reporting metrics is approved.
  2. Update the WBS to include 'Earned Schedule Analysis' as a new work package.
  3. Instruct the finance department to stop tracking AC since the focus is now on time.
  4. Stop all EVM data collection and focus only on the critical path in the schedule model, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials