easy · Project Management Professional Predictive (Plan-Driven)

Larkspur Health has a $500,000 budget for a medical device project. The PM calculates that spending $10,000 on additional design reviews will save $40,000 in rework costs. In CoQ terms, the PM is proposing to increase:

  1. Direct costs to decrease indirect costs.
  2. Appraisal costs to decrease external failure costs.
  3. Prevention costs to decrease internal failure costs.
  4. Internal failure costs to increase prevention costs.

Sign up free to see the explanation and track your rank →