medium · Project Management Professional Predictive (Plan-Driven)

Ironvale Grid is managing a project with a 'hard logic' dependency where the electrical substation foundation must be cured before the transformers are installed.

This is an example of which dependency type?

  1. External dependency.
  2. Mandatory dependency.
  3. Discretionary dependency.
  4. Start-to-Start dependency.

Sign up free to see the explanation and track your rank →