medium · Project Management Professional Predictive (Plan-Driven)

Fenwick Grid is upgrading its transmission lines. The project is behind schedule. The project manager decides to use crashing.

To be effective, which activities should the project manager target first?

  1. Activities that the team finds the most difficult to complete.
  2. Activities with the most total float to ensure they don't become critical.
  3. Activities on the critical path with the lowest crash cost per unit of time.
  4. Activities that have not yet started, regardless of their path.