At Fenwick Grid, a project manager is summarizing 'lessons learned' for a phase gate. They notice that the team frequently struggled with a specific local zoning law.

To create a usable OPA, what should the PM do?

  1. Create a 'Zoning Compliance Guide' with specific contact names and lead times for that jurisdiction.
  2. Note 'Zoning was difficult' in the final report and close the project documentation.
  3. Instruct the next project manager to hire a legal consultant to handle all future zoning issues.
  4. Escalate the zoning law issue to the Governor's office to request a permanent legislative change.