Whitlock Software is migrating a client to a new ERP. Several key users are resisting the change, stating that they understand the benefits but feel they haven't been given enough time to learn the new interface.

Using the ADKAR model, where is the barrier to change?

  1. Knowledge
  2. Reinforcement
  3. Desire
  4. Ability