medium · Project Management Professional predictive
Harborline Transit is constructing a new rail terminal using a predictive approach. The critical path activity 'Signal Integration' has duration estimates of O=12 days, M=15 days, and P=24 days.
Using the Beta distribution, what is the expected duration (t_E)?
- 16.0 days
- 18.0 days
- 17.0 days
- 15.0 days