Harborline Transit is constructing a new rail terminal using a predictive approach. The critical path activity 'Signal Integration' has duration estimates of O=12 days, M=15 days, and P=24 days.

Using the Beta distribution, what is the expected duration (t_E)?

  1. 16.0 days
  2. 18.0 days
  3. 17.0 days
  4. 15.0 days