medium · Project Management Professional predictive

An activity at Northwick Clinics has an optimistic estimate of 10 days, a most likely estimate of 16 days, and a pessimistic estimate of 28 days.

Using the PERT (Beta) distribution, what is the expected duration (t_E) and the activity standard deviation (σ)?

  1. T_E = 16 days; σ = 6 days
  2. T_E = 18 days; σ = 3 days
  3. T_E = 17 days; σ = 1.5 days
  4. T_E = 17 days; σ = 3 days

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials