An activity at Northwick Clinics has an optimistic estimate of 10 days, a most likely estimate of 16 days, and a pessimistic estimate of 28 days.
Using the PERT (Beta) distribution, what is the expected duration (t_E) and the activity standard deviation (σ)?
- T_E = 16 days; σ = 6 days
- T_E = 18 days; σ = 3 days
- T_E = 17 days; σ = 1.5 days
- T_E = 17 days; σ = 3 days
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?