An activity in the Cinderwell Water pipeline project has three estimates for its duration: Optimistic = 4 days, Most Likely = 7 days, and Pessimistic = 16 days.
Using the PERT (Beta) formula, what is the expected duration?
- 7.0 days
- 10.0 days
- 8.0 days
- 9.0 days