easy · Project Management Professional Predictive (Plan-Driven)

Animal Shelter Expansion at Westfork: PV = $450,000, EV = $400,000, AC = $400,000.

What are the indices?

  1. CPI = 0.89; SPI = 1.00
  2. CPI = 1.13; SPI = 1.00
  3. CPI = 1.00; SPI = 1.13
  4. CPI = 1.00; SPI = 0.89

Sign up free to see the explanation and track your rank →