Whitlock Software is using a Requirements Traceability Matrix (RTM) for a secure portal. A gap is found: a high-priority security requirement is not linked to any design element or test case.

What does this gap primarily indicate?

  1. The project is at risk of failing its quality audit and not meeting its acceptance criteria.
  2. The project manager should immediately add a new activity to the schedule to build the missing feature.
  3. The project scope has crept, and the RTM must be updated to remove the requirement.
  4. The customer should be notified that the security requirement cannot be met in this release.