medium · Project Management Professional predictive

A project manager at Valeport Energy finds that 'Crashing' a specific activity has hit 'diminishing returns.'

What does this mean in a predictive schedule context?

  1. The activity has moved off the critical path.
  2. The cost of crashing is now lower than the normal cost of the activity, while documenting the decision in the issue log.
  3. The activity is now being fast-tracked instead of crashed.
  4. The activity cannot be shortened any further regardless of how many resources are added.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials