A project manager at Valeport Energy finds that 'Crashing' a specific activity has hit 'diminishing returns.'

What does this mean in a predictive schedule context?

  1. The activity has moved off the critical path.
  2. The cost of crashing is now lower than the normal cost of the activity, while documenting the decision in the issue log.
  3. The activity is now being fast-tracked instead of crashed.
  4. The activity cannot be shortened any further regardless of how many resources are added.